Since 2005, the Town of Battleford has received and allocated $6,011,148.52 through the federal Build Communities Strong Fund (BCSF), formerly know as the Gas Tax Fund.
The funding allows municipal leadership to address aging infrastructure, upgrade core utilities, and invest in local recreational spaces without placing the full financial burden on local property taxpayers.
How the $6.01M Funding Has Been Distributed (2005-2029)
|
Infrastructure Category |
Allocated Amount |
% of Total Investment |
Key Featured Projects |
|
Recreation |
$3,184,018.56 |
53.0% |
Sports Arena Expansion, Arena Ice Plant & Roof, 15th St Walking Path |
|
Roads & Sidewalks |
$2,477,334.47 |
41.2% |
Street Reconstruction (23rd St, W, 25th St), 1st/2nd Ave Sidewalks |
|
Utilities |
$349,795.49 |
5.8% |
WTP Backup Generator, WTP SCADA System Upgrades |