3rd Avenue Crescent Infrastructure Upgrades

The Town of Battleford is launching a comprehensive water and sewer replacement project along 3rd Avenue Crescent.

 

Click or tap the map image above to open it in full size. 

 

🟢 CURRENT UPDATE: September 29, 2026

3rd Avenue Crescent – Infrastructure Replacement Update

Sanburn Construction has completed the water and sewer infrastructure replacement project along 3rd Avenue Crescent.

Restoration work along 3rd Avenue Crescent will take place in the near future. Curbing and asphalt crews will be starting soon as the project moves into the restoration phase.

Residents and motorists are asked to continue using caution around construction areas and to follow posted signage and traffic-control measures

200 Block of 21st Street – Water Service Restored

Repairs on the 200 block of 21st Street have now been completed, and water services have been restored.

Residents may initially experience air in the water lines and/or discoloured water. If this occurs, please run the water until a steady flow is established and the water runs clear.

Important: A Boil Water Advisory remains in effect for affected residents until further notice. Residents are advised to follow all instructions associated with the advisory until it has been officially lifted.

Thank you for your patience and caution as we work to improve our community's infrastructure!



September 22, 2026

  • Final Stages: Infrastructure replacement of the mains is now in the final stage, with the remaining work progressing from 21st Street to 3rd Avenue.  The contractor is expected to complete the remaining distribution repairs on or around September 30, 206.
  • Site Activity & Surface Work: As the project moves toward completion, asphalt and curbing crews will also be working in the area.  Residents should expect construction equipment, temporary access restrictions, and other construction-related activity while this work is completed.
  • Work Completed: The infrastructure replacement work from 19th Street to part of 21st Street has been completed.

  • Upcoming Water Disruptions (100 Block of 21st Street West): Residents in the 100 block of 21st Street West should be aware that temporary water disruptions are expected over the coming weeks as the remaining work is completed.

  • Resident Notices: Notices will be hand-delivered to affected residents as construction schedules are confirmed and as time permits.  Residents are encourage to plan accordingly and watch for additional notices from the Town regarding upcoming water interruptions.


September 14, 2026

Infrastructure work along 3rd Avenue Crescent is moving right along:

  • Pipe Replacement: Initial underground pipe replacement south of 20th Street is near completion. Crews will now continue replacing pipes heading north toward 21st Street West.

  • Paving & Concrete: Paving crews will soon begin preparing the site for new concrete curbing and fresh asphalt.

August 17, 2026

Current Work & Next Steps:

  • Water & Sewer Replacement: Crews will be digging and starting underground water and sewer main replacement specifically along 19th Street to 20th Street.

  • Traffic & Access: Road closures and local traffic detours remain in effect around the active construction zones. Please exercise caution, watch for workers, and obey all posted signage and barricades.

August 10, 2026

Contractors will be onsite this week to begin excavating.

  • Local traffic and parking will be restricted
  • Loose bagged garbage will be picked up behind the residences affected during this upgrade.
  • Compost will be picked Mondays by calling the Town to schedule a pick up.

July 27, 2026

  • Boil Water Advisory Lifted: The Drinking Water Advisory for the 200 blocks of 18th, 19th, and 20th Streets, as well as portions of 3rd Avenue Crescent, has been officially rescinded. Water is safe for normal use.
  • Upcoming Work on 3rd Avenue Crescent: Construction and infrastructure work on 3rd Avenue Crescent is scheduled to begin August 10. Motorists and residents are asked to use caution in the area.


July 20, 2026

  • On the Ground: Hydrant and valve replacement on the 200 Block of 20th Street West commences today, July 20, 2026. Active construction will begin at approximately 7:30 a.m. on Tuesday, July 21, 2026. Work is expected to last roughly one day, weather permitting.

  • Water Hookups & Disruptions: Affected residents will be entirely without water for the day while replacements are underway. Temporary water service interruptions will impact:

    • 252 – 296 of 20th Street West

    • 301, 311, and 321 of 21st Street West (only)

  • Traffic & Access Impact: Expect increased construction activity, high noise levels, temporary traffic disruptions, and limited access near the immediate work area.

⚠️ Precautionary Boil Water Advisory (PBWA) Once water service is restored, properties at 252–296 20th Street West and 301, 311, 321 21st Street West will be placed under a PBWA.

The advisory will remain in effect until the Saskatchewan Health Authority laboratory returns satisfactory test results from collected samples. Residents will be directly notified as soon as the advisory is officially lifted.

 

July 16, 2026

The Town of Battleford would like to advise residents that, due to unforeseen circumstances, the planned hydrant and valve replacement on the 200 Block of 19th Street West has been rescheduled.

Work Area

Construction activities will take place on:

  • 200 Block of 19th Street West

ยท         Date: Monday, July 20, 2026; Time: Beginning at approximately 7:30 a.m.

Residents in the following areas will be subject to a temporary water service interruption while this work is being completed:

  • 200 Block of 18th Street West
  • 200 Block of 19th Street West
  • 301–333 3rd Avenue Crescent

The work is expected to last approximately one day (weather permitting).

Precautionary Boil Water Advisory (PBWA)

Once the work has been completed and water service has been restored, residents on the 200 Block of 18th Street West, 200 Block of 19th Street West, 301 to 333 of 3rd Avenue Crescent, will be placed under a Precautionary Boil Water Advisory (PBWA).


Week of July 13 – July 17, 2026

Work Area & Impacts

  • Location: 200 Block of 19th Street West
  • Work Includes: Valve and hydrant replacements, and underground infrastructure work.
  • Expect: Increased noise, traffic disruptions, temporary access restrictions, and short-term water interruptions (advance notice will be provided).

Precautionary Boil Water Advisory (PBWA)

Once water service is restored, the 200 block of 19th Street only will be placed under a PBWA.

The advisory will remain in effect until Saskatchewan Health Authority lab tests confirm the water is safe. Residents will be notified as soon as it is officially lifted.

The Town appreciates your patience during these infrastructure upgrades.


Week of July 6 – July 10, 2026

  • On the Ground: Site mobilization is underway. Crews are currently arriving on-site with heavy machinery and replacing main valves.

  • Water Hookups: Installation of the temporary overland water line is actively being laid out.

  • Traffic Impact: 3rd Avenue Crescent is experiencing temporary lane restrictions and rolling closures between 19th and 21st Street. Commuters are advised to use alternate routes.

  • Waste Collection: Standard pickup is currently running. Residents facing direct blockages will receive direct notice regarding modified bin placement.

 


📅 Estimated Project Schedule (Subject to Weather)

  • Mobilization & Temporary Water Setup
July 6 – July 10

Crews arrive on site, begin valve replacements, and install the temporary overland water system.

  • Water & Sewer Replacements (20th St to 19th St)
July 13 – July 31

Deep utility excavation, main replacements, services, and stubs begin from 20th Street to 19th Street.

  • Main Work Moves (20th St to 21st St)
Aug 4 – Aug 21

Water and sewer replacements move from 20th Street to 21st Street. Road base work begins from 19th Street to 20th Street.

  • Main Work Moves (21st St to 3rd Ave)
Aug 24 – Sept 11

Water and sewer replacements move from 21st Street to 3rd Avenue. Road base work shifts from 20th Street to 21st Street.

  • Testing & Switching Off Temporary Water
Sept 14 – Sept 18

Final block road base work, watermain testing, camera inspections, and the removal of all temporary water lines.

  • Surface Rebuilding & Paving
Sept 21 – Oct 15

Curb installation, sidewalk/pathway reconstruction, and final road paving.

  • Final Site Cleanup
Oct 19 – Oct 23

Demobilization and final site cleanup.